Wilson Boulevard Extension/Benfield Road Corridor Study
Wilson Boulevard Extension / Benfield Road Corridor Study
Over the past ten to fifteen years, Transportation Planning has conducted many planning projects and corridor studies to provide technical assistance for Collier County. Many of these studies were based on needs in Collier MPO’s 2025, 2030 and 2035 Long Range Plans. These studies were done in cooperation with local jurisdictions, FDOT and extensive outreach with the private sector and the public. The following list of past projects is meant as a reference with historical information about the project/plan/report or study. In several instances, once the final project/plan/report or study has been presented to the Board of County Commissioners, no further action has been or is anticipated to be taken.
The Collier MPO is in a unique position to create a vision for all of Collier County (including the Cities of Everglades City, Marco Island, Naples and unincorporated Collier County). The MPO’s planning across the jurisdictions helps set the plan for Collier County Transportation Planning. The current studies that Collier County Transportation Planning is starting to embark on were derived from the Collier MPO’s 2040 Long Range Transportation Plan.
Future planning studies identified in the Collier MPO's 2040 LRTP Needs Plan:
1. Randall Blvd. / Oil Well Road Study Area
2. Green Blvd. Ext. / North Belle Meade Study Area
3. CR951 Congestion Relief Study
The CR951 Area Study is designed to help examine the feasibility and potential impacts of developing improvements to a corridor extending east of CR 951 to Benfield Road and from the Lord’s Way to City Gate Blvd. North and including the parcels of property already owned by Collier County. Transportation Planning understands that a number of east-west and north-south corridors have already been considered by the Wilson Blvd. Ext. / Benfield Rd. Corridor Study. A future area study would update the recommendations of that study to determine the need, feasibility and a preferred alignment for the identified corridor. There is currently no funding identified for this study. More information regarding this future study is expected after the MPO adopts the 2045 LRTP.
For more information, please contact Transportation Planning, at 239-252-8192.
The following information is for historical reference and was last updated in April 2010.
The Study was initiated by the Collier County Transportation Planning Department in July 2007. The area studied is approximately 20 miles long and 9 miles wide, bordered by US 41 to the south, CR 951/Collier Boulevard to the west, Golden Gate Boulevard to the north and Everglades Boulevard to the east. The Collier County Growth Management Plan requires transportation system enhancements to maintain the adopted roadway level of service to accommodate approved and anticipated development. The existing CR 951 facility serves as the primary corridor for north-south mobility connecting Marco Island to the northern limit of Collier County at Immokalee Road and is planned to be extended into Lee County. Although growth along the corridor has subsided due to the current economic downturn, the development of remaining land in Golden Gate Estates and along the corridor will ultimately causes the CR 951 facility to fail.
The need for a north-south arterial road was identified in the Collier Metropolitan Planning Organization (MPO) 2030 Long Range Transportation Plan approved by the Board of County Commissioners on January 12, 2006. The Collier MPO 2030 LRTP minor update approved by the MPO Board on June 8, 2007 maintained the need for this facility. The Wilson Boulevard Extension / Benfield Road facility is identified in the 2030 LRTP as a financially feasible project.
Public input has been sought throughout the study process. Since the study began in 2007, Collier County has conducted a series of public outreach events, including two major public workshops, the Benfield Road community meeting, the Verona Walk community meeting and other meetings/presentations to agencies, associations (Golden Gate Estates Area Civic Association), stakeholders and groups such as Leadership Collier. Many of the meetings and coordination efforts were conducted by County staff, with participation by the Consultant Team. In addition, two newsletters were prepared and information was posted on the County’s website to provide project information and updates. In addition, meetings were held with environmental and other government agencies and individual property owners to discuss the project alternatives in detail and to obtain comments. It is important to note that these comments received by the county have been documented, reviewed, and in some cases, accounted for by additions, deletions or /modifications of the proposed alternative alignments.
The Study was refined to consider the following alternatives:
No Build
Although a no build condition was modeled, capacity improvements may be considered should there be no alternate parallel roadway constructed in an effort to reduce congestion and delay. This may include geometric enhancements at key intersections within the corridor, widening CR 951 to an eight lane condition, enhancements at the I-75 interchange, and new interchanges at key locations such as US 41.
Alternative 2: Miller Boulevard
The Miller Boulevard alternative would provide a north/south connection to the Collier County Hurricane Evacuation Route Plan. It would improve access to the interstate system for evacuees during an emergency event and improve regional evacuation and emergency response time.
Portions of Alternative 2 currently exist as Miller Boulevard, a non-functionally classified local roadway. In order for this alternative to be viable, this facility would be upgraded to meet current design standards. As with the No Build scenario, an eight-lane facility within the vicinity of I-75 does not provide sufficient capacity to achieve acceptable LOS.
Conclusion and Recommendations
Utilizing feedback from the workshops, technical analysis, and collaboration with Collier County Transportation staff, the consultants have produced a final Study report with the following conclusions and recommendations:
- The No Build alternative would not only result in increased congestion on CR 951/Collier Boulevard, but would also encourage diversion to adjacent parallel facilities west of CR 951/Collier Boulevard therefore increasing congestion on those facilities.
- Under the No Build alternative, additional portions of the CR951/Collier Boulevard corridor will ultimately fail shortly after the 2035 study year. Similarly, congestion on parallel facilities west of CR 951/Collier Boulevard would increase.
- With or without the construction of an additional north-south corridor, the interchange at I-75 and CR 951/Collier Boulevard will require a complete reconstruction prior to the year 2035. Estimates have ranged between $125 million and $250 million depending on the limits of the reconstruction.
- Alternative 2 (Miller Boulevard) does not provide significant relief to CR 951/Collier Boulevard, however it does provide a secondary connection between development along the US 41, Marco Island and Golden Gate Estates. It also provides an excellent opportunity for an emergency evacuation route. Due to the significant environmental impacts and the minimal mobility benefit, this alternative would not satisfy the requirements identified in the purpose and need statement of this corridor study.
- Alternative 3A/3B (Wilson / Benfield) would provide significant relief to CR 951/Collier Boulevard and adjacent parallel facilities.
- Costs associated with each build alternative prohibit the feasibility of constructing this facility as one project. However, it should be noted that alternative 3A/3B is approximately twenty miles long and represents a corridor that would be developed in phases concurrently with development and growth along the corridor.
- Florida Rock Industries, Inc. which entered into a Developer Contribution Agreement with the County on June 26, 2007 is moving forward with their project. The agreement requires the developer to provide to the County 60% Design Plans for the roadway to be located within the Wilson Boulevard Extension as identified in the North Belle Meade Overlay of the GMP.