The Collier County Water Sewer District has plans to expand potable water services to Golden Gate City. This project installs transmission water mains which are large, pressurized pipes that will connect to regional water mains on Collier Boulevard and Santa Barbara Boulevard/Radio Road.
The project is separated into phases 1A, 1B and 2. Phase 1A constructs the transmission water main traveling through the Golden Gate Golf Course in Golden Gate City. Phase 1B includes construction of the transmission water main from the golf course to connect to the existing water main at Santa Barbara Boulevard and Radio Road. Phase 2 includes construction of the transmission water main traveling near Santa Barbara Boulevard, Green Boulevard, 15th Avenue SW and 48th Street SW. For more information about the project, visit Golden Gate City Transmission project website.
Project design was completed in 2022 and construction of Phase 1A is anticipated to be complete Summer 2024, Phase 1B is anticipated to be complete Summer 2025, and Phase 2 is anticipated to be complete Winter 2025.